Class Tsk
- java.lang.Object
-
- com.aspose.tasks.Tsk
-
-
Field Summary
Fields Modifier and Type Field Description static Key<String,Integer>ACTIVITY_IDRepresents activity id field - a task's unique identifier used by Primavera.static Key<BigDecimal,Integer>ACTUAL_COSTCosts incurred for work already performed by resources on their tasks, together with any other recorded costs associated with the task.static Key<Duration,Integer>ACTUAL_DURATIONThe span of actual working time for a task, based on the scheduled duration and current remaining work or percent complete.static Key<Date,Integer>ACTUAL_FINISHThe date when a task was completed.static Key<BigDecimal,Integer>ACTUAL_OVERTIME_COSTCosts incurred for overtime work already performed on tasks by assigned resources.static Key<Duration,Integer>ACTUAL_OVERTIME_WORKThe actual amount of overtime work already performed by resources assigned to tasks.static Key<Duration,Integer>ACTUAL_OVERTIME_WORK_PROTECTEDThe duration through which actual overtime work is protected.static Key<Date,Integer>ACTUAL_STARTThe date and time that a task actually began.static Key<Duration,Integer>ACTUAL_WORKThe amount of work that has already been done by resources assigned to tasks.static Key<Duration,Integer>ACTUAL_WORK_PROTECTEDThe duration through which actual work is protected.static Key<Double,Integer>ACWPCosts incurred for work already done on a task, up to the project status date or today's date.static Key<Double,Integer>BCWPThe cumulative value of the task's percent complete multiplied by the time phased baseline costs.static Key<Double,Integer>BCWSThe cumulative time phased baseline costs up to the status date or today's date.static Key<BigDecimal,Integer>BUDGET_COSTBudget costs for budget cost resources.static Key<Duration,Integer>BUDGET_WORKBudget work for budget work and material resources.static Key<Calendar,Integer>CALENDARThe task calendar.static Key<Date,Integer>COMMITMENT_FINISHThe finish date of a delivery.static Key<Date,Integer>COMMITMENT_STARTThe start date of a delivery.static Key<Integer,Integer>COMMITMENT_TYPEDetermines whether a task has an associated delivery or a dependency on an associated delivery.static Key<Date,Integer>CONSTRAINT_DATEThe specific date associated with the constraint type.static Key<Integer,Integer>CONSTRAINT_TYPEProvides choices for the type of constraint that can be applied for scheduling a task.static Key<String,Integer>CONTACTThe name of an individual responsible for a task.static Key<BigDecimal,Integer>COSTThe total scheduled or projected cost for a task based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work.static Key<Double,Integer>COST_VARIANCEThe difference between the baseline cost and total cost for a task, resource, or assignment.static Key<Date,Integer>CREATEDThe date when a task was created.static Key<Double,Integer>CVThe difference between the baseline cost and total cost for a task.static Key<Date,Integer>DEADLINEA target date that indicates when a task is to be completed.static Key<NullableBool,Integer>DISPLAY_AS_SUMMARYDetermines whether the task should be displayed as a summary task.static Key<Boolean,Integer>DISPLAY_ON_TIMELINESpecifies whether a task should be displayed on a timeline view.static Key<Duration,Integer>DURATIONThe total span of active working time for a task as entered or as calculated by Microsoft Project based on start date, finish date, calendars, and other scheduling factors.static Key<Integer,Integer>DURATION_FORMATTask duration format.static Key<String,Integer>DURATION_TEXTReturns the task's duration text.static Key<Duration,Integer>DURATION_VARIANCEThe difference between the baseline duration of a task and the total duration (current estimate) of a task.static Key<Date,Integer>EARLY_FINISHThe earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay.static Key<Date,Integer>EARLY_STARTThe earliest date that a task could possibly begin, based on the early start dates of predecessor and successor tasks and other constraints.static Key<Integer,Integer>EARNED_VALUE_METHODDetermines whether the % Complete or Physical % Complete field should be used to calculate budgeted cost of work performed (BCWP).static Key<Integer,Integer>EXTERNAL_IDIf a task is an external task it contains the task's external Id.static Key<String,Integer>EXTERNAL_TASK_PROJECTThe source location and task identifier of an external task.static Key<Date,Integer>FINISHThe scheduled finish date of a task.static Key<Integer,Integer>FINISH_SLACKThe duration (in tenths of a minute) between the Early Finish and Late Finish dates.static Key<String,Integer>FINISH_TEXTReturns the task's finish text.static Key<Duration,Integer>FINISH_VARIANCEThe time that represents the difference between the baseline finish date of a task or assignment and its current finish date.static Key<Double,Integer>FIXED_COSTShows any non resource task expense.static Key<Integer,Integer>FIXED_COST_ACCRUALDetermines choices for how and when fixed costs are to be charged, or accrued, to the cost of a task.static Key<Integer,Integer>FREE_SLACKThe time (in tenths of a minute) that a task can be delayed without delaying any successor tasks.static Key<String,Integer>GUIDThe generated unique identification codes for a task.static Key<NullableBool,Integer>HAS_OVERALLOCATED_RESOURCEIndicates whether the task has an resource assigned which has more work on assigned tasks than can be completed within normal working capacity.static Key<NullableBool,Integer>HIDE_BARDetermines whether the Gantt bar of a task is hidden when displayed in Microsoft Project.static Key<String,Integer>HYPERLINKThe title or explanatory text for a hyperlink associated with a task.static Key<String,Integer>HYPERLINK_ADDRESSThe address for a hyperlink associated with a task.static Key<String,Integer>HYPERLINK_SUB_ADDRESSThe specific location in a document in a hyperlink associated with a task.static Key<Integer,Integer>IDThe position identifier of a task within the list of tasks.static Key<NullableBool,Integer>IGNORE_RESOURCE_CALENDARDetermines whether the scheduling of the task considers the calendars of the resources assigned to the task.static Key<Boolean,Integer>IGNORE_WARNINGSIndicates whether to hide the schedule conflict warning indicator in Microsoft Project.static Key<NullableBool,Integer>IS_ACTIVEDetermines whether a task is active.static Key<NullableBool,Integer>IS_CRITICALDetermines whether a task is on the critical path.static Key<NullableBool,Integer>IS_EFFORT_DRIVENDetermines whether the scheduling for the task is effort-driven scheduling.static Key<NullableBool,Integer>IS_ESTIMATEDDetermines whether a task is estimated.static Key<NullableBool,Integer>IS_EXPANDEDDetermines whether a summary task is expanded or not in GanttChart view.static Key<Boolean,Integer>IS_EXTERNAL_TASKDetermines whether a task is external.static Key<NullableBool,Integer>IS_MANUALDetermines whether a task is manually scheduled.static Key<Boolean,Integer>IS_MARKEDShows whether a task is marked for further action or identification of some kind.static Key<NullableBool,Integer>IS_MILESTONEDetermines whether a task is a milestone.static Key<NullableBool,Integer>IS_NULLDetermines whether a task is a null task.static Key<NullableBool,Integer>IS_OVERALLOCATEDIndicates whether any of the assigned resources on a task is assigned to more work on the task than can be done withing the normal working capacity.static Key<NullableBool,Integer>IS_PUBLISHEDDetermines whether the current task should be published to Project Server with the rest of the project.static Key<NullableBool,Integer>IS_RECURRINGDetermines whether a task is part of a series of recurring tasks.static Key<NullableBool,Integer>IS_RESUME_VALIDDetermines whether a task can be resumed.static Key<NullableBool,Integer>IS_ROLLUPDetermines whether information about the subtask Gantt bars will be rolled up to the summary task bar.static Key<Boolean,Integer>IS_SUBPROJECTDetermines whether a task is an inserted project.static Key<NullableBool,Integer>IS_SUBPROJECT_READ_ONLYDetermines whether a subproject is read-only.static Key<Boolean,Integer>IS_SUMMARYDetermines whether a task is a summary task.static Key<Date,Integer>LATE_FINISHThe latest date that a task can finish without delaying the finish of the project.static Key<Date,Integer>LATE_STARTThe latest date that a task can start without delaying the finish of the project.static Key<NullableBool,Integer>LEVEL_ASSIGNMENTSDetermines whether the leveling function can delay and split individual assignments in order to resolve over allocations.static Key<NullableBool,Integer>LEVELING_CAN_SPLITDetermines whether the resource leveling function can cause splits on remaining work on this task.static Key<Duration,Integer>LEVELING_DELAYThe time that a task is to be delayed from its early start date because of resource leveling.static Key<Integer,Integer>LEVELING_DELAY_FORMATThe format of expressing the duration of a delay.static Key<Duration,Integer>MANUAL_DURATIONDefines manually scheduled duration of a task.static Key<Date,Integer>MANUAL_FINISHDefines manually scheduled finish of a task.static Key<Date,Integer>MANUAL_STARTDefines manually scheduled start of a task.static Key<String,Integer>NAMEA task's name.static Key<String,Integer>NOTES_RTFThe text notes in RTF format.static Key<String,Integer>NOTES_TEXTNotes' plain text extracted from RTF data.static Key<Integer,Integer>OUTLINE_LEVELThe outline level of a task.static Key<String,Integer>OUTLINE_NUMBERThe number that represents a task's position in the hierarchical outline structure.static Key<BigDecimal,Integer>OVERTIME_COSTThe total overtime cost for a task, for a resource on all assigned tasks, or for a resource assignment.static Key<Duration,Integer>OVERTIME_WORKThe amount of overtime scheduled to be performed by all resources assigned to a task.static Key<Integer,Integer>PERCENT_COMPLETEThe current status of a task, expressed as the percentage of the task's duration that has been completed.static Key<Integer,Integer>PERCENT_WORK_COMPLETEThe current status of a task expressed as the percentage of work that has been completed.static Key<Integer,Integer>PHYSICAL_PERCENT_COMPLETEPercent complete value that can be be used as an alternative for calculating budgeted cost of work performed (BCWP).static Key<Date,Integer>PRELEVELED_FINISHThe finish date of a task as it was before resource leveling was done.static Key<Date,Integer>PRELEVELED_STARTThe start date of a task as it was before resource leveling was done.static Key<Integer,Integer>PRIORITYThe level of importance given to a task, which in turn indicates how readily a task or assignment can be delayed or split during resource leveling.static Key<Duration,Integer>REGULAR_WORKThe total amount of non overtime work scheduled to be performed by resources.static Key<BigDecimal,Integer>REMAINING_COSTThe remaining scheduled expense that will be incurred in completing the remaining scheduled work.static Key<Duration,Integer>REMAINING_DURATIONThe time that is required to complete the unfinished part of a task.static Key<BigDecimal,Integer>REMAINING_OVERTIME_COSTThe remaining scheduled overtime expense for a task.static Key<Duration,Integer>REMAINING_OVERTIME_WORKThe amount of remaining scheduled overtime time.static Key<Duration,Integer>REMAINING_WORKThe time still required to complete a task or set of tasks.static Key<Date,Integer>RESUMEThe date that the remaining part of a task is scheduled to resume after entering any progress.static Key<Date,Integer>STARTThe scheduled start date of a task.static Key<Integer,Integer>START_SLACKThe duration (in tenths of a minute) between the Early Start and Late Start dates.static Key<String,Integer>START_TEXTReturns the task's start text.static Key<Duration,Integer>START_VARIANCEThe time that represents the difference between a baseline start date of a task or assignment and its currently scheduled start date.static Key<String,Integer>STATUS_MANAGERThe name of the enterprise resource who is to receive status updates for the current task from resources.static Key<Date,Integer>STOPThe date that represents the end of the actual portion of a task.static Key<String,Integer>SUBPROJECT_NAMEThe source location of a subproject.static Key<Double,Integer>SVThe earned value schedule variance, through the project status date.static Key<Integer,Integer>TOTAL_SLACKThe time (in tenths of a minute) a task's finish date can be delayed without delaying the project's finish date.static Key<Integer,Integer>TYPEThe type of a task.static Key<Integer,Integer>UIDThe unique Id of a task.static Key<Boolean,Integer>WARNINGRepresents the flag which indicates that task has schedule discrepancies.static Key<String,Integer>WBSWork breakdown structure (WBS) codes.static Key<String,Integer>WBS_LEVELThe rightmost WBS level of a task.static Key<Duration,Integer>WORKThe total time scheduled on a task for all assigned resources.static Key<Duration,Integer>WORK_VARIANCEThe difference between baseline work of a task and the currently scheduled work.
-
Constructor Summary
Constructors Constructor Description Tsk()
-
-
-
Field Detail
-
ID
public static final Key<Integer,Integer> ID
The position identifier of a task within the list of tasks.
-
IS_NULL
public static final Key<NullableBool,Integer> IS_NULL
Determines whether a task is a null task.
-
CONTACT
public static final Key<String,Integer> CONTACT
The name of an individual responsible for a task.
-
OUTLINE_NUMBER
public static final Key<String,Integer> OUTLINE_NUMBER
The number that represents a task's position in the hierarchical outline structure.
-
PRIORITY
public static final Key<Integer,Integer> PRIORITY
The level of importance given to a task, which in turn indicates how readily a task or assignment can be delayed or split during resource leveling.
-
DURATION
public static final Key<Duration,Integer> DURATION
The total span of active working time for a task as entered or as calculated by Microsoft Project based on start date, finish date, calendars, and other scheduling factors.
-
DURATION_VARIANCE
public static final Key<Duration,Integer> DURATION_VARIANCE
The difference between the baseline duration of a task and the total duration (current estimate) of a task.
-
WORK
public static final Key<Duration,Integer> WORK
The total time scheduled on a task for all assigned resources.
-
STOP
public static final Key<Date,Integer> STOP
The date that represents the end of the actual portion of a task.
-
RESUME
public static final Key<Date,Integer> RESUME
The date that the remaining part of a task is scheduled to resume after entering any progress.
-
IS_RESUME_VALID
public static final Key<NullableBool,Integer> IS_RESUME_VALID
Determines whether a task can be resumed.
-
IS_EFFORT_DRIVEN
public static final Key<NullableBool,Integer> IS_EFFORT_DRIVEN
Determines whether the scheduling for the task is effort-driven scheduling.
-
IS_RECURRING
public static final Key<NullableBool,Integer> IS_RECURRING
Determines whether a task is part of a series of recurring tasks.
-
IS_SUMMARY
public static final Key<Boolean,Integer> IS_SUMMARY
Determines whether a task is a summary task.
-
IS_OVERALLOCATED
public static final Key<NullableBool,Integer> IS_OVERALLOCATED
Indicates whether any of the assigned resources on a task is assigned to more work on the task than can be done withing the normal working capacity.
-
HAS_OVERALLOCATED_RESOURCE
public static final Key<NullableBool,Integer> HAS_OVERALLOCATED_RESOURCE
Indicates whether the task has an resource assigned which has more work on assigned tasks than can be completed within normal working capacity.
-
IS_ESTIMATED
public static final Key<NullableBool,Integer> IS_ESTIMATED
Determines whether a task is estimated.
-
IS_MILESTONE
public static final Key<NullableBool,Integer> IS_MILESTONE
Determines whether a task is a milestone.
-
IS_CRITICAL
public static final Key<NullableBool,Integer> IS_CRITICAL
Determines whether a task is on the critical path.
-
IS_SUBPROJECT
public static final Key<Boolean,Integer> IS_SUBPROJECT
Determines whether a task is an inserted project.
-
IS_SUBPROJECT_READ_ONLY
public static final Key<NullableBool,Integer> IS_SUBPROJECT_READ_ONLY
Determines whether a subproject is read-only.
-
IS_MARKED
public static final Key<Boolean,Integer> IS_MARKED
Shows whether a task is marked for further action or identification of some kind.
Applies to mpp file format only.booleantype.
-
IGNORE_WARNINGS
public static final Key<Boolean,Integer> IGNORE_WARNINGS
Indicates whether to hide the schedule conflict warning indicator in Microsoft Project.
-
IS_EXTERNAL_TASK
public static final Key<Boolean,Integer> IS_EXTERNAL_TASK
Determines whether a task is external.
-
SUBPROJECT_NAME
public static final Key<String,Integer> SUBPROJECT_NAME
The source location of a subproject.
-
EXTERNAL_TASK_PROJECT
public static final Key<String,Integer> EXTERNAL_TASK_PROJECT
The source location and task identifier of an external task.
-
EXTERNAL_ID
public static final Key<Integer,Integer> EXTERNAL_ID
If a task is an external task it contains the task's external Id.
-
EARLY_START
public static final Key<Date,Integer> EARLY_START
The earliest date that a task could possibly begin, based on the early start dates of predecessor and successor tasks and other constraints.
-
EARLY_FINISH
public static final Key<Date,Integer> EARLY_FINISH
The earliest date that a task could possibly finish, based on early finish dates of predecessor and successor tasks, other constraints, and any leveling delay.
-
LATE_START
public static final Key<Date,Integer> LATE_START
The latest date that a task can start without delaying the finish of the project.
-
LATE_FINISH
public static final Key<Date,Integer> LATE_FINISH
The latest date that a task can finish without delaying the finish of the project.
-
START_VARIANCE
public static final Key<Duration,Integer> START_VARIANCE
The time that represents the difference between a baseline start date of a task or assignment and its currently scheduled start date.
-
FINISH_VARIANCE
public static final Key<Duration,Integer> FINISH_VARIANCE
The time that represents the difference between the baseline finish date of a task or assignment and its current finish date.
-
WORK_VARIANCE
public static final Key<Duration,Integer> WORK_VARIANCE
The difference between baseline work of a task and the currently scheduled work.
-
COST_VARIANCE
public static final Key<Double,Integer> COST_VARIANCE
The difference between the baseline cost and total cost for a task, resource, or assignment.
-
START_SLACK
public static final Key<Integer,Integer> START_SLACK
The duration (in tenths of a minute) between the Early Start and Late Start dates.
Can be converted to TimeSpan using the following expression: TimeSpan.FromMinutes(task.Get(Tsk.StartSlack) / 10). The return type of this property will be changed to TimeSpan in next major release (22.1).
-
FINISH_SLACK
public static final Key<Integer,Integer> FINISH_SLACK
The duration (in tenths of a minute) between the Early Finish and Late Finish dates.
Can be converted to TimeSpan using the following expression: TimeSpan.FromMinutes(task.Get(Tsk.FinishSlack) / 10). The return type of this property will be changed to TimeSpan in next major release (22.1).
-
FREE_SLACK
public static final Key<Integer,Integer> FREE_SLACK
The time (in tenths of a minute) that a task can be delayed without delaying any successor tasks.
Can be converted to TimeSpan using the following expression: TimeSpan.FromMinutes(task.Get(Tsk.FreeSlack) / 10). The return type of this property will be changed to TimeSpan in next major release (22.1).
-
TOTAL_SLACK
public static final Key<Integer,Integer> TOTAL_SLACK
The time (in tenths of a minute) a task's finish date can be delayed without delaying the project's finish date.
Can be converted to TimeSpan using the following expression: TimeSpan.FromMinutes(task.Get(Tsk.TotalSlack) / 10). The return type of this property will be changed to TimeSpan in next major release (22.1).
-
FIXED_COST_ACCRUAL
public static final Key<Integer,Integer> FIXED_COST_ACCRUAL
Determines choices for how and when fixed costs are to be charged, or accrued, to the cost of a task.
-
PERCENT_COMPLETE
public static final Key<Integer,Integer> PERCENT_COMPLETE
The current status of a task, expressed as the percentage of the task's duration that has been completed.
-
PERCENT_WORK_COMPLETE
public static final Key<Integer,Integer> PERCENT_WORK_COMPLETE
The current status of a task expressed as the percentage of work that has been completed.
-
COST
public static final Key<BigDecimal,Integer> COST
The total scheduled or projected cost for a task based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work.
-
OVERTIME_COST
public static final Key<BigDecimal,Integer> OVERTIME_COST
The total overtime cost for a task, for a resource on all assigned tasks, or for a resource assignment.
-
ACTUAL_START
public static final Key<Date,Integer> ACTUAL_START
The date and time that a task actually began.
-
ACTUAL_FINISH
public static final Key<Date,Integer> ACTUAL_FINISH
The date when a task was completed.
-
ACTUAL_DURATION
public static final Key<Duration,Integer> ACTUAL_DURATION
The span of actual working time for a task, based on the scheduled duration and current remaining work or percent complete.
-
ACTUAL_COST
public static final Key<BigDecimal,Integer> ACTUAL_COST
Costs incurred for work already performed by resources on their tasks, together with any other recorded costs associated with the task.
-
ACTUAL_OVERTIME_COST
public static final Key<BigDecimal,Integer> ACTUAL_OVERTIME_COST
Costs incurred for overtime work already performed on tasks by assigned resources.
-
ACTUAL_WORK
public static final Key<Duration,Integer> ACTUAL_WORK
The amount of work that has already been done by resources assigned to tasks.
-
ACTUAL_OVERTIME_WORK
public static final Key<Duration,Integer> ACTUAL_OVERTIME_WORK
The actual amount of overtime work already performed by resources assigned to tasks.
-
REGULAR_WORK
public static final Key<Duration,Integer> REGULAR_WORK
The total amount of non overtime work scheduled to be performed by resources.
-
OVERTIME_WORK
public static final Key<Duration,Integer> OVERTIME_WORK
The amount of overtime scheduled to be performed by all resources assigned to a task.
-
REMAINING_DURATION
public static final Key<Duration,Integer> REMAINING_DURATION
The time that is required to complete the unfinished part of a task.
-
REMAINING_COST
public static final Key<BigDecimal,Integer> REMAINING_COST
The remaining scheduled expense that will be incurred in completing the remaining scheduled work.
-
REMAINING_WORK
public static final Key<Duration,Integer> REMAINING_WORK
The time still required to complete a task or set of tasks.
-
REMAINING_OVERTIME_WORK
public static final Key<Duration,Integer> REMAINING_OVERTIME_WORK
The amount of remaining scheduled overtime time.
-
REMAINING_OVERTIME_COST
public static final Key<BigDecimal,Integer> REMAINING_OVERTIME_COST
The remaining scheduled overtime expense for a task.
-
ACWP
public static final Key<Double,Integer> ACWP
Costs incurred for work already done on a task, up to the project status date or today's date.
-
CV
public static final Key<Double,Integer> CV
The difference between the baseline cost and total cost for a task. Cost Variance = Cost - Baseline Cost
-
SV
public static final Key<Double,Integer> SV
The earned value schedule variance, through the project status date. Schedule variance (SV) is the difference between the BCWP and the BCWS.
-
CONSTRAINT_TYPE
public static final Key<Integer,Integer> CONSTRAINT_TYPE
Provides choices for the type of constraint that can be applied for scheduling a task.
-
CONSTRAINT_DATE
public static final Key<Date,Integer> CONSTRAINT_DATE
The specific date associated with the constraint type.
-
DEADLINE
public static final Key<Date,Integer> DEADLINE
A target date that indicates when a task is to be completed.
-
LEVEL_ASSIGNMENTS
public static final Key<NullableBool,Integer> LEVEL_ASSIGNMENTS
Determines whether the leveling function can delay and split individual assignments in order to resolve over allocations.
-
LEVELING_CAN_SPLIT
public static final Key<NullableBool,Integer> LEVELING_CAN_SPLIT
Determines whether the resource leveling function can cause splits on remaining work on this task.
-
LEVELING_DELAY
public static final Key<Duration,Integer> LEVELING_DELAY
The time that a task is to be delayed from its early start date because of resource leveling.
-
LEVELING_DELAY_FORMAT
public static final Key<Integer,Integer> LEVELING_DELAY_FORMAT
The format of expressing the duration of a delay.
-
PRELEVELED_START
public static final Key<Date,Integer> PRELEVELED_START
The start date of a task as it was before resource leveling was done.
-
PRELEVELED_FINISH
public static final Key<Date,Integer> PRELEVELED_FINISH
The finish date of a task as it was before resource leveling was done.
-
HYPERLINK
public static final Key<String,Integer> HYPERLINK
The title or explanatory text for a hyperlink associated with a task.
-
HYPERLINK_ADDRESS
public static final Key<String,Integer> HYPERLINK_ADDRESS
The address for a hyperlink associated with a task.
-
HYPERLINK_SUB_ADDRESS
public static final Key<String,Integer> HYPERLINK_SUB_ADDRESS
The specific location in a document in a hyperlink associated with a task.
-
IGNORE_RESOURCE_CALENDAR
public static final Key<NullableBool,Integer> IGNORE_RESOURCE_CALENDAR
Determines whether the scheduling of the task considers the calendars of the resources assigned to the task.
-
HIDE_BAR
public static final Key<NullableBool,Integer> HIDE_BAR
Determines whether the Gantt bar of a task is hidden when displayed in Microsoft Project.
-
IS_ROLLUP
public static final Key<NullableBool,Integer> IS_ROLLUP
Determines whether information about the subtask Gantt bars will be rolled up to the summary task bar.
-
BCWS
public static final Key<Double,Integer> BCWS
The cumulative time phased baseline costs up to the status date or today's date.
-
BCWP
public static final Key<Double,Integer> BCWP
The cumulative value of the task's percent complete multiplied by the time phased baseline costs.
-
PHYSICAL_PERCENT_COMPLETE
public static final Key<Integer,Integer> PHYSICAL_PERCENT_COMPLETE
Percent complete value that can be be used as an alternative for calculating budgeted cost of work performed (BCWP).
-
EARNED_VALUE_METHOD
public static final Key<Integer,Integer> EARNED_VALUE_METHOD
Determines whether the % Complete or Physical % Complete field should be used to calculate budgeted cost of work performed (BCWP).
-
ACTUAL_WORK_PROTECTED
public static final Key<Duration,Integer> ACTUAL_WORK_PROTECTED
The duration through which actual work is protected.
Reading supported for XML format only.DURATIONtype.
-
ACTUAL_OVERTIME_WORK_PROTECTED
public static final Key<Duration,Integer> ACTUAL_OVERTIME_WORK_PROTECTED
The duration through which actual overtime work is protected.
Reading supported for XML format only.DURATIONtype.
-
IS_PUBLISHED
public static final Key<NullableBool,Integer> IS_PUBLISHED
Determines whether the current task should be published to Project Server with the rest of the project.
-
STATUS_MANAGER
public static final Key<String,Integer> STATUS_MANAGER
The name of the enterprise resource who is to receive status updates for the current task from resources.
-
COMMITMENT_TYPE
public static final Key<Integer,Integer> COMMITMENT_TYPE
Determines whether a task has an associated delivery or a dependency on an associated delivery.
Reading supported for XML format only.inttype.
-
IS_MANUAL
public static final Key<NullableBool,Integer> IS_MANUAL
Determines whether a task is manually scheduled.
-
IS_EXPANDED
public static final Key<NullableBool,Integer> IS_EXPANDED
Determines whether a summary task is expanded or not in GanttChart view.
-
GUID
public static final Key<String,Integer> GUID
The generated unique identification codes for a task.
-
NOTES_TEXT
public static final Key<String,Integer> NOTES_TEXT
Notes' plain text extracted from RTF data.
-
MANUAL_START
public static final Key<Date,Integer> MANUAL_START
Defines manually scheduled start of a task.
-
MANUAL_FINISH
public static final Key<Date,Integer> MANUAL_FINISH
Defines manually scheduled finish of a task.
-
MANUAL_DURATION
public static final Key<Duration,Integer> MANUAL_DURATION
Defines manually scheduled duration of a task.
-
BUDGET_WORK
public static final Key<Duration,Integer> BUDGET_WORK
Budget work for budget work and material resources. Budget resources are assigned only to the project summary task.
-
BUDGET_COST
public static final Key<BigDecimal,Integer> BUDGET_COST
Budget costs for budget cost resources. Budget resources are assigned only to the project summary task.
-
DISPLAY_AS_SUMMARY
public static final Key<NullableBool,Integer> DISPLAY_AS_SUMMARY
Determines whether the task should be displayed as a summary task.
Reading supported for XML format only.booleantype.
-
IS_ACTIVE
public static final Key<NullableBool,Integer> IS_ACTIVE
Determines whether a task is active. Inactive tasks no longer affect other tasks or the overall Project schedule.
-
DURATION_TEXT
public static final Key<String,Integer> DURATION_TEXT
Returns the task's duration text.
-
DISPLAY_ON_TIMELINE
public static final Key<Boolean,Integer> DISPLAY_ON_TIMELINE
Specifies whether a task should be displayed on a timeline view.
-
WARNING
public static final Key<Boolean,Integer> WARNING
Represents the flag which indicates that task has schedule discrepancies.
-
-